V3.3.2 [2013-05-01]
- Bug fixing : #1085, #1086
V3.3.1 [2013-04-29]
- Bug fixing : #1079, #1080, #1081, #1082
V3.3.0 [2013-04-27]
- Fully configurable Today screen :
- select tasks board to be displayed
- select period of tasks to be displayed (based on due date)
- display any report on today screen
- reorder boards
- print today screen
- Planning improvements :
- high performance improvements on Gantt display : this is no more a mess for large plannings
- possibility to fix planning for a project (and its sub-projects)
- gantt display : save of selected scale and position of vertical splitter
- new scale : quarter
- new "portfolio of projects" Gantt view
- Test Sessions improvement
- test sessions can be assigned and planned, like activities
- test sessions can have hierarchic structure : parent session (to define session of sessions) or parent activity (to set hierarchic position in the gantt)
- alerts can be managed on test sessions (indicators can be defined on test sessions)
- test sessions are listed on tasks lists on the today screen
- eMailing improvements :
- parametering of subject and message sent on user account information
- new events for automatic emailing : on note change, on description change, on result change, on new assignment, on assignment change, on any change
- mail to assigned resources
- Other miscellanous improvemens
- do not close a projet with not closed items
- document and version naming convention
- direct access to items selected in Filtering Select lists
- Bug fixing : #1035, #1036, #1037, #1038, #1039, #1040, #1041, #1042, #1056, #1059, #1065, #1068, #1069
V3.2.2 [2013-03-25]
- Bug fixing : #1033, #1034
V3.2.1 [2013-03-17]
- User manual completion
- Translations completion
- Bug fixing : #944, #1018, #1019, #1021, #1022, #1023, #1025
V3.2.0 [2013-03-10]
- Planning improvement :
- improvement of the move of tasks with drag & drop
- create link between tasks with drag & drop on Gantt
- add priority and planning mode in columns
- possibility to sort dispayed columns
- keep visibility of selected line in Gantt view
- Real work allocation improvement :
- performance improvement (notable for complex projets)
- selection of displayed period through calendar
- display function for assignment
- Connections management :
- list of open sessions
- possibility to close one session or all sessions
- open / close of application for maintenance operations
- Responsible management eased :
- automatic set responsible for projects with single affectation
- automatic update Responsible when status comes to in progress
- Project improvement :
- add health of project
- display heath on Today screen
- close affectations on project closure
- Opportunity & Risk improvement :
- User improvement :
- initialize password
- defined default profile
- Bug fixing : #689, #878, #969, #971, #976, #977, #995, #996, #997, #1007, #1012
V3.1.4 [2013-02-10]
- Bug fixing : #968, #974, #975, #980, #998, #999
V3.1.3 [2013-02-04]
V3.1.2 [2013-02-03]
V3.1.1 [2013-01-20]
V3.1.0 [2013-01-14]
- Global performance improvement for large databases (many proijects) with complex projects hierarchy
- Real work allocation improvement :
- control that day work is not over resource capacity
- submission of week by resource
- validation of week by manager
- locking submitted / validated work
- comment field available for each week
- New Simple Ticket : simplified screen for ticket input, to be opened wide to many users
- Adding Opportunities management
- New filter operators
- Activity : new "expected" progress, calculated as (Real Work) / (Validated Work)
- Action : efficiency added
- Requirement : new locking functionality
- Improvements on import :
- truncate fields to max size,
- remove spaces to numbers,
- control of format,
- replacement of "Word" special quote
- Meeting : when sending eMail from meeting, list of attendees is automatically added in recipients list
- Indent projects in list to represent wbs
- New "Term" report
- Force javascript files refresh on each new version, to avoid cache issues
- Bug fixing : #668, #811, #825, #922, #925, #926, #927, #928, #934, #937, #939, #940, #943, #945, #947, #949, #955, #956
V3.0.2 [2012-12-03]
- Bug fixing : #905, #911, #918, #920, #921
V3.0.1 [2012-11-25]
- Chinese translation
- Bug fixing : #891, #893, #894, #897, #902, #903, #904, #906, #912, #913
V3.0.0 [2012-11-12]
- Database access
- Full PDO implementation : it opens connectivity to several database systems
- Alert on configuration if PDO is not enabled on PHP
- Transactional updates on every database update
- PostgreSql compatibility : you can now choose Database format between MySql and PostgreSql
- Multiple versions on Ticket
- Provide multi selection for versions on Ticket for target version and Origin version
- Version reports can use mono version or multple versions
- Import improvements
- Possible input of all data for progress (on activity) or Origin (on ticket)
- Improved management of header set as caption instead of column id
- Possibility to import foreign references as name of the reference instead of id of the reference
- Parameters
- All parameters, except database parameters and log parameters, moved to database
- Parameters are now updatable through the global parameters screen
- Deployment improvement
- Restart Cron on deployment to take into account new files and classes
- Readme and licence text files included in projectorria directory
- User Manual
- User manual completion, up to date with V3.0.
- Removal of many typos.
- Bug fixing : #824, #879, #881, #882, #883, #884, #885, #886
V2.6.3 [2012-10-29]
V2.6.2 [2012-10-22]
- Add possibility to import items with a defined id
- Bug fixing : #837, #838, #839, #842
V2.6.1 [2012-10-16]
V2.6.0 [2012-10-13]
- Cleaner login interface
- Email improvements
- Possibility to send email on responsible change
- Possibility to send email on note add
- Possibility to send email to project manager
- Possibility to send email at wish : new "email" button on mailable items
- Email is sent with complete formatted item detail, including notes
- Direct link to item in the email
- Copy improvements
- New status 'copied' : copied items are copied into this new status, and must be moved to 'recorded' to start workflow
- When copying item, can also copy links, attachments and notes
- When copying an activity, can copy its whole structure (sub-activities)
- When copying a project with structure, can also copy sub-projects
- When copying from planning view, stay on planning view
- Improved error message displayed if error occured during copy
- Requirement is now copyable, into Ticket or else
- Automated integration
- All files put in a defined directory will automatically be imported
- Files just have to be named "Class_Timestamp.csv" (for instance "Ticket_20121221.csv") to import items of class "Class"
- Expected format for files is the standard Import format
- Possibility to email log of integration result
- Add product to Ticket
- Product can now be selected on Ticket
- When selecting the product, origin and target version lists are restricted to product list
- When selecting a version, product is set if it was not
- Filtering on Product also lists Tickets linked to sub-products
- Parameters moved to database (part 1, to be completed in next version)
- Email parameters are moved to the database
- Parameters stored in the databse can then be updated through the Global Parameters screen
- "parameter.php" file is updated to remove these paramerters
- If a parameter exists in the database and in the parameters.php file, the value is extracted from the file version
- Others
- Project is now linkable : project can be linked to any other linkable item
- Planning pdf export now fits 1 page large (many thanks to Estelle for this very usefull improvement)
- Direct access to an item with a direct link url : this way, link to item is added in the detailed email
- Privacy restriction (private or public) to notes and attachments
- Definition of predefined text for notes
- Requirement can now have an Origin
- For lists, add default sort on name, if "sort order" field is not defined, or for equal values of "sort order"
- Bug fixing : #556, #693, #779, #798, #790, #791, #792, #799, #801, #803, #804, #809, #815, #816, #818, #822
V2.5.3 [2012-10-16]
V2.5.2 [2012-09-17]
V2.5.1 [2012-09-10]
- Bug fixing : #771, #772 , #773 , #774 , #775 , #776 , #777
V2.5.0 [2012-09-02]
- This version brings technical improvements :
- Integration of Dojo V1.8.0 : optimizing performance and stability (particularly on FireFox)
- History update for add/update/delete of link, note and attachment
- Improve performance on first page login (noticeable for databases with large number of projects)
- Use of PDO library for persistence : updates are now transactionnal, for best database consistency
- Add Team parameter to Resource reports
- Bug fixing : #753, #756, #757, #759
V2.4.3 [2012-08-07]
V2.4.2 [2012-08-05]
- New improvement on selection of "Linked elements", "Approvers" and "Test case run" :
- multi-selection is now possible in the complete detailed list
- filters and textual quick search are now operational in the complete detailed list
- Summary field for Requirements, Test sessions and Test cases as indicator of global tests status
- Translation into russian (thanks to Anrysys)
- Bug fixing : #736, #737, #738, #739, #743, #745
V2.4.1 [2012-07-29]
- Implementation of new Dojo version : V1.7.3+ (version between V1.7.3 and V1.7.4, fixing identified issues)
- Formated display of dates in history
- Bug fixing : #725, #725, #728, #729, #730, #731, #732, #733, #735
V2.4.0 [2012-07-16]
- Tests management : definition of test cases, definitions of test sessions, assignment of tests to sessions
- Requirements management : definition of requirements, link to tests, display of test coverage
- Improvement of dependencies : possibility to define a delay between tasks, defining overlap if negative
- New report : Detailed monthly activity planning per Project / Activity / Resource
- GUI improvments : possibility to print history, quick search also serches in notes
- Bug fixing : #672, #697, #705, #709, #712, #719, #720
V2.3.0 [2012-06-09]
- Planning improvement :
- add new "work" columns
- add possibility to select displayed columns
- calculation improvement : fiability of priority and dependency constraints
- save collapsed / expand status of each line
- Gantt printing improvement : print collapsed levels as displayed, print resource if displayed
- checkboxes to collapse / expand all levels of lines
- New Resource Gantt planning screen
- including above improvements
- Bug fixing : #684, #685, #686, #687, #692, #695
V2.2.3 [2012-05-19]
- Bug fixing : #674, #675, #676, #677, #678, #680, #681
V2.2.2 [2012-05-13]
V2.2.1 [2012-05-12]
- Bug fixing : #658, #659, #660, #661, #662, #663, #664, #666,, #667, #669
V2.2.0 [2012-05-06]
- Work for tickets :
- Timer to indicate start and stop of work
- Work period on Timer saved as real work
- Real work automatically saved as real work allocation :
- on activity if ticket has a Planning Activity
- on not assigned item in other cases
- Document approval process
- Set possibility to link any item to any other item
- Meeting attendees improvement :
- meeting list managed as mail reveivers list : just entrer names or initilas, separated by commas, and the list will be transformed including email in "gmail like" format
- possibility to send an invitation for meeting to attendees (in "outlook meeting" format)
- GUI improvements :
- Calendar screen simplified
- Possibility to change logo : Just insert your own logo.gif at the root directory will automatically replace displayed logo
- New operators for filters : "is empty" and "is not empty"
- Save Start and End dates for planning display
- Lock screen when an operation is ongoing
- Attachments can be a hyperlink (url) not only a downloaded file
- Hyperlinks for project to give quick access to external web pages of files
- Limit visibility and update capacity on real work allocation for other users, depending on current user's project visibility
- New indicators for Activitiy :
- real work compared to validated work
- real work compared to assigned work
- New report "detailed version status", listing all items included in the version
- Import : possibility to import Products and Versions
- Password automatically set to default value on user creation
- Reports : header added on reports to be displayed on printed sheets
- Bug fixing : #635, #637, #639, #640, #641, #642, #643, #647, #650, #651, #653, #654, #655
V2.1.1 [2012-04-08]
- Bug fixing : #504, #608, #618, #623, #624, #625, #626, #629, #630, #631
V2.1.0 [2012-03-29]
- Improved planning :
- improved calculation performance
- taking into account dependencies of parent tasks
- display name or initiales of resource on Gantt bars
- don't display administrative project tasks in Gantt planning
- add end date to limit display
- Eased affectations :
- resources don't have to be affected and assigned to adminitrative project tasks
- direct affectation of all team members to a project
- Extended data for tickets :
- add notion of duplicate
- add work follow-up : planned and real
- context : 3 parameterable elements for environment description
- Improved access to product documents
- Add Product - Sub-product hierarchy
- New report : version status, summarize planned and real work
- Minor GUI improvment
- display progress (%) in progress section (for activities and projects)
- workflow for projects
- add target version in list of activities
- increase list of fileds to use in mail message
- today screen made more easy to understand
- multiple select in link list
- User manual completed
- Bug fixing : #548, #588, #592, #596, #598, #600, #601, #603, #604, #610, #612, #614, #615, #617, #618
V2.0.1 [2012-02-19]
- Bug fixing : #555, #559, #560, #561, #562, #563, #564, #567, #569, #574, #575
V2.0.0 [2012-02-06]
- Document management is now included in Project'Or RIA
- As always, it is kept easy to use
- Documents are imported at version management
- Status is managed on each version, with workfow enabled
- Id of version managed is several ways : evolutive (as Vx.y), chronological (as a date), sequential (as a number) or external (manually defined)
- Easy lock and unlock document, to reserve editing
- Direct download
- Financial functionality :
- Definition of billing type on project type
- Several billing types defined : Fixed price, Time & Material, Caped Time & Material, Manual
- Definition of blling terms (for fixed price)
- Definition of Activity price (for Time & Material)
- Management of bills
- Management of bill lines depending on billing type
- Bill edition (template provided, to be apdated to your own needs)
- User interface improvments :
- Read only fileds are displays with visual status to point out they are readonly
- All sections are collapsable, and status (collpsed or expanded) is restored at last status on each screen)
- When dialog form is opened, use [CTRL]+S to save
- Target date added to version in combo box display
- On planning, collapsed status for groups is restored on each access and is reproduced as is in printed form
- On real work input screen, collapsed status for groups is restored on each access and is reproduced as is in printed form
- Description added to meetings
- Improved controls :
- Control of double input in delay for ticket definition
- Control of double input in Mail on status change definition
- Add planning rights management, to avoid having any resource being able to plan the project
- Improved Admin functionalities :
- Recalculate reference for any (or all) type of element
- auto-relaunch cron (alert sender) on user connection if is was abnormaly ended (php stopped)
- Bug fixing : #516, #502, #507, #523, #53&, #532, #534, #539, #541, #542, #543
V1.9.1 [2012-01-03]
- Bug fixing : #503, #511, #512, #515, #522
V1.9.0 [2011-12-10]
- Export the planning to MS-Project xml format
- Export every list to CSV Format : likely to be opened in MS-Excel; likely to be-re-imported in Import functionality
- Base copy of project to copy the entire structure of the project (activities, mielstones, links)
- Add type of project
- Specific type of project "Template", to be copied as new projet, visible for every project manager, without need of an affectation
- Add direct access for "add" or "update" or "delete" to affectations from Project and from Resource
- Add direct access to stored filters, in a tooltip list
- Add new filter on dates with a generic date, such as <= today + 7 days (so filter is up to date every day)
- Add a Reference for most items, provinding a unique numbering for each type, within a parametered format
- Automatically create new affectation for Project Manager, when defined
- Column "target version" added in Tickets list
- Add attachments and notes on Projects
- Add requestor to activities (similar ot Ticket requestor field)
- Add target dates for version ("Enter Into Service" and "End")
- Bug fixing : #457, #467, #471, #472 , #478, #481, #482, #483, #487, #491, #496
V1.8.3 [2011-11-03]
V1.8.2 [2011-10-29]
V1.8.1 [2011-10-22]
- Bug fixing : #439, #445, #446, #447, #448, #449, #453
V1.8.0 [2011-10-18]
- Reminders and alerts
- LDAP connectivity
- Choose unit as days or hours for Real work imputation and / or work follow-up
- Translation to spanish
- Administration screen
- Global parameter screen
- User interface improvements
- Automatic check of version upon last released version
- Bug fixing : #400, #417, #418, #423, #424, #425, #426, #428, #429, #430, #436Bug fixing : #410, #415, #416
V1.7.2 [2011-09-14]
- Bug fixing : #410, #415, #416
V1.7.1 [2011-09-06]
- German translation for V1.7.0
- Bug fixing : #402, #404
V1.7.0 [2011-09-04]
- Add calendar management :
- a week day may be off,
- a week-end day may be worked.
- Add product an version Management.
Possibility to store origin version on tickets, and target version on tickets, activities and milestones.
- Possibility to assign contacts and users to projects, to provide a visibility corresponding to the profile rights.
- Possibility to import expense.
- Improved navigation :
- New menu bar, with quick access buttons,
- history of consulted items, with possibility to navigate through it.
- Add possibility to copy an item into a new one of another king (for instance copy a ticket as an activity).
- Avoid sending email on copy of item : wait until first save.
- Add origin management, with possibility to store origin when copying an item. So it is possible to store that an activity has a ticket as its origin.
- New theme, used as defaut, with colors of web site.
- Give choice (as user parameter) to print or pdf export into a new page or in a included frame.
- Bug fixing #373, #375, #380, #386, #389, #391, #393, #395, #396, #397.
V1.6.2 [2011-08-09]
- Bug fixing #371, #372, #379.
V1.6.1 [2011-07-24]
- Bug fixing #342, #343, #346, #347, #348, #349, #351, #353, #354, #355, #356, #357, #358, #360, #361, #362, #363, #366.
V1.6.0 [2011-06-15]
- Improvement of Today Screen :
- Add Questions, Meetings and Decisions in Projects summary
- Add for each item a visual progress bar, depending on item status (open, done, closed)
- Add expense Management :
- Individual expense (travel cost, ...)
- Project expense
- Add "Search" functionality for combo lists :
- Display a "search" button next to the combo
- Clic on "search" button displays the full selectable list of elements
- If item is not found in the list, it is possible to directly create a new one ("New" button)
- If combo is not empty, clic on "search" button will first display the detail of the item, with possible access to search list
- Add quick search functionality, searching on any text field and on the id
- New reports :
- Resource availability plan
- Detail of activity, per task, per user, per day
- Expense reports
- Global summary for Expense and Resource cost
- Generalization of Export to PDF (for any print functionality)
- Add possibility to attach files to Actions
- Description field moved to bottom (to see other items if description is very long)
- Limit Database update to "admin" :
- When installing new version, connections are refused for non admin users
- Bug fixing #304, #313, #318, #320, #322, #325, #326, #328, #329, #336, #337, #338.
V1.5.5 [2011-02-22]
V1.5.4 [2011-02-18]
- Bug fixing #306, #308, #309.
V1.5.3 [2011-02-16]
- Bug fixing #302, #303, #304, #305, #306.
V1.5.2 [2011-02-09]
- Additions to Manual.
- Add tag search in Manual.
- Bug fixing #299, #300.
V1.5.1 [2011-02-05]
- Improved reports for PDF format.
- Translation to German of V1.5 texts.
- Additions to Manual.
- Bug fixing #297.
V1.5.0 [2011-01-29]
- Add cost management:
- Add notion of function (role).
- Resource has default function (main function).
- Daily cost is stored on Resource, for a given function.
- Assignment to an activity uses function to get daily cost.
- Real work allocation calculates global cost for activity and project.
- Cost is displayed face to work.
- Add management of visibility of Cost and Work depending on profile.
- Add Requestor to Ticket description (a Requestor is a Contact).
- Extend possibility to automatically send email on status change to :
- Requestor,
- Project Leader
- Fixed email list
- Extend filter functionality to be able to sort result.
- Improve of Workflow display :
- Colums header is repeated before each line.
- Line header is repeated as last column.
- Added a graphical Workflow Diagram to display possible progress on status.
- Add possibility to export Reports as PDF.
This functionality is proposed as beta-test, some reports have to be adapted to be correctly display in PDF format.
- Add possibility to store GUI behaviour as user parameter:
- Show/Hide Menu.
- Switched mode between list and detail.
New behavior also includes possiblity to choose how to switch modes:
- On mouse over the shrinked bar.
- On click on the shrinked bar.
- Improve language change : when changing language, screen is completely refreshed to be displayed using new language.
- Display WBS on Project and Activity.
- Add list of Affectations on Project description.
- Add list of Affectations on Resource description.
- Add list of Projects on Customer description.
- Add Urgency in header for Tickets.
- Bug fixing #287, #288, #289, #290.
V1.4.2 [2010-12-05]
- Bug fixing #238, #272.
- Improve manual : new subjects, related topics links.
V1.4.1 [2010-12-01]
- Bug fixing #262, #263, #264, #265, #266.
V1.4.0 [2010-11-27]
- Online Manual. Hit [F1] to open Manual.
This is the first version of manual, with generic information. Detail for each screen to come next.
Contextual access if page corresponding to actual screen exists.
- New language for interface : German.
Thanks to Klaus for his work on translation.
- Access right management for reports and real work input.
- Activities ordering in Planning - Gantt view : just drap and drop the activity to move it.
- Two new planning modes for activities : fixed duration, and regular in half days.
- Hide/Show menu functionaity, with automatic show/hide.
- Switched mode, to switch between list and detail, to have a "full screen" view of detail.
- Add possibility to set a filter as default, to automatically retrieve it on each connection.
- Limit parent activity list to the activities of the same project.
- Limit responsible list to the resources affected to the project.
- Add notion of contact, for customer contact, with full address.
- Extension of import functionality to Project, Meetings, Decisions, Questions and Affectations.
- Help on format for each import.
- Linked elements are now selectable : it's possible to move from actions, risks ans issues through links.
- Integration of Dojo 1.5 : fields are not truncated any more on the right.
- 11 new color themes, with light color (pastel) and contrasted color.
- Severity field added to issues.
- Bug fixing #212, #231, #234, #236, #237, #238, #240, #241, #242, #246, #249, #252, #256, #259.
V1.3.1 [2010-11-06]
- Correction to have Project'Or RIA work when 'erro_log' function is disabled by provider.
V1.3.0 [2010-10-31]
- Graphical reports.
- New reports for tickets summary.
- New reports for workload summary.
- New reports for work status summary.
- New reports for planning data.
- New reports for history access, including deleted items.
- Add access right management for reports.
- Add printing facility for imputation.
- Add access restriction for imputations.
- Rapid save with [ctrl]+'s'.
- Improvement of due dates initialization.
- Add possibility to set result mandatory on done items.
- Add possibility to set description mandatory depending on type of items.
- Add 'handled' status.
- Add possibility to set responsible mandatory on handled items.
- Improvement of configuration form.
- Bug fixing #201, #210, #214, #221, #224, #225, #227, #228.
- 1 new parameter defined, to set default theme (used on login page).
V1.2.1 [2010-10-05]
- Bug fixing #204, #208, #209.
V1.2.0 [2010-09-29]
- Meetings management.
- Decisions management.
- Questions management.
- Automatic email generation on status change.
- Planning calculation optimization.
- Bug fixing #185, #191, #192.
- 6 new parameters defined, for email management.
V1.1.0 [2010-08-22]
- Printable reports.
- Possibility to print Gantt planning.
- Possibility to print lists.
- Bug fixing #180, #181, #182.
V1.0.1 [2010-07-13]
V1.0.0 [2010-07-05]
- Name change : ProjectOr becomes Project'Or RIA, for Project Organizer Rich Internet Application.
This will allow :
- distinction with light products ;-)
- easy finding in search engine, using 'projectorria' keyword.
- Automatic parameters configuration screen at first run.
- Advanced filter functionality.
- On Today screen, summary of activities for connected user, with direct link to each item.
- On Today screen, possibility to count done and closed items for projects summary.
- Display of dates corresponding to locale, in every field (including lists).
- Display number of elements in main list grid.
- Improvement of copy functionality ; initialization of some data that should not be copied.
- Add priority management for Actions.
- Bug corrections #162, #163, #167, #170, #172, #173, #174, #175.
V0.9.0 [2010-06-02]
- Workflow management for status change limitation.
- Lock closed elements (except status and 'closed' flag).
- Minor bug corrections #157, #158, #159.
V0.8.1 [2010-05-20]
- Minor bug corrections #155, #156.
V0.8.0 [2010-04-17]
- Improvement in planning algorythm, taking into account resource capacity, resource affectation rate to project and resource assignment rate to activity.
- Change closure management and add done status as checkbox.
- Automatically update closure and done on status update.
- Compute real start and end dates corresponding to work on the activity.
- Add controls on delete request for an item to cancel the operation if dependant elements exist.
- Remove week-ends in duration calculation so that duration is in work days.
V0.7.0 [2010-04-16]
- First Release Candidate version.
- Add dependency management between Activities, Milestones and Projects.
- Planning calculation taking into account dependencies.
- Show dependencies on Gantt planning chart.
- Add import functionality, to import elements from CSV files.
- Show planned work on work follow-up screen.
V0.6.1 [2010-02-27], V0.6.2 [2010-03-07]
- Correction of issues appearing in hosted mode.
V0.6.0 [2010-02-14]
- Add management of assignment to activities.
- Add workload follow-up.
V0.5.0 [2009-11-12]
- Add links between Actions, Issues and Risks.
- Add link of Activity, Ticket or Milestone to parent Activity (hierarchic level management).
V0.4.0 [2009-10-13]
- Add Team element to gather resources.
- Increase performance (loading time highly reduced).
V0.3.0 [2009-10-05]
- Add work follow-up : Tickets, Activities, Milestones.
- Add planning display as Gantt chart.
- Add message management.
V0.2.0 [2009-08-18]
- Add rights access management at Project level, completely customizable.
- Improved adaptability of detail display to fit window size.
- Few bugs correction (including incorrect menu indentation)
V0.1.0 [2009-06-25]
- First version, to implement technical elements.
This version is limited to some parameters and Risk Management Plan : Risks, Actions and Issues Management.